Skip to content

New Schools

PROPERTY DESCRIPTIONACRESPROPOSED PROJECTOFFSITE DEVELOPMENTPROPOSED START SCHEDULE
The Coves at Winfield Subdivision20Alexander HS New 9th Grade CampusBy Killam Development:
Street, Utilities Extension
Site work:  Aug 2014
Utilities:     Oct 2014
Building:    Dec 2014
Killam Charco Ranch, North International Blvd.20United HS New 9th Grade CampusBy Killam Development:
Street, Utilities Extension
Site work:  Aug 2014
Utilities:     Oct 2014
Building:    Dec 2014
Eloy Garcia Ranch HWY 35920New Middle SchoolBy UISD:
Street, Utilities Extension
Site work:  Aug 2014
Utilities:     Oct 2014
Building:    Dec 2014
San Isidrio North Subdivision10New Elementary SchoolNoneSite work:   July  2014
Utilities:      Aug  2014
Building:     Sept 2014
Eloy Garcia Ranch HWY 35911New Elementary SchoolBy UISD:
Street, Utilities Extension
Site work:   July  2014
Utilities:      Aug  2014
Building:     Sept 2014
Cuatro Vientos North Subdivision18United South HS New 9th Grade CampusNoneSite work:   May  2015
Utilities:      July  2015
Building:     Sept 2015
Cielito Lindo Subdivision20L. B. Johnson HS New 9th Grade CampusBy UISD:
Street, Utilities Extension
Site work:   May  2015
Utilities:      July  2015
Building:     Sept 2015
Cuatro Vientos North Subdivision10New Elementary SchoolNoneSite work:   May  2015
Utilities:      June 2015
Building:     July  2015
Cielito Lindo Subdivision14New Elementary SchoolNoneSite work:   May  2015
Utilities:      June 2015
Building:     July  2015
Aqueros Sudbivision, Mines Rd.35New Middle SchoolBy UISD:
Street, Utilities Extension
Site work:   Dec  2015
Utilities:       Feb  2016
Building:     April 2016
Cuatro Vientos Sur Subdivision20New Middle SchoolNoneSite work:   Dec  2015
Utilities:       Feb  2016
Building:     April 2016
The Coves at Winfield Subdivision (Shiloh)12New Elementary SchoolBy Killam Development:
Street, Utilities Extension
Site work:   Dec  2016
Utilities:       Feb 2017
Building:     April 2017